Electricity Public Company announces distribution of loads manually.
Pulbished on:
Tripoli, 26.04.2015(Lana) Electricity Public Company announced
distribution of loads manually and for long hours in Tripoli, Central
area and Sebha to safeguard safety and stability of the network until
maintenance of disconnected lines is completed.
In a statement, the company explained that due to disconnection
of 400 KV and 220 KV lines linking the Western area, Tripoli region
and central area due to ongoing developments in the Western area, it
has to distribute the load manually and for long hours daily.
It said, it lost 1000 Megawat of production capacity at Zawia and
Rawiss generation stations. The company urged consumers to ration
energy consumption daily.